  • Construction bids for Streetcar Project over budget

    Construction bids for Streetcar Project over budget

    Thursday, February 14 2013 10:13 PM EST2013-02-15 03:13:39 GMT
    Construction bids for the Cincinnati Streetcar project have come in tens of millions of dollars over what a project budget shows the city had anticipated. The bids include the cost to construct 3.6 milesFull Story >
    Construction bids for the Cincinnati Streetcar project have come in tens of millions of dollars over what a project budget shows the city had anticipated. The bids include the cost to construct 3.6 miles of streetcar tracks as well as stations and a maintenance and operations facility. Full Story >
  • City, Duke reach agreement on streetcar

    City, Duke reach agreement on streetcar

    Friday, February 1 2013 7:40 PM EST2013-02-02 00:40:41 GMT
    After two years of talks, Duke Energy has agreed to begin relocating the utilities along the Cincinnati Streetcar route. Cincinnati Mayor Mark Mallory and City Manager Milton Dohoney, Jr.  made the announcement on Friday.Full Story >
    After two years of talks, Duke Energy has agreed to begin relocating the utilities along the Cincinnati Streetcar route. Cincinnati Mayor Mark Mallory and City Manager Milton Dohoney, Jr.  made the announcement on Friday.Full Story >
  • Cincinnati streetcar project delayed again

    Cincinnati streetcar project delayed again

    Friday, January 4 2013 7:39 PM EST2013-01-05 00:39:53 GMT
    The new Cincinnati streetcar project has been delayed again. Now the city is saying it won't be ready for riders until the spring of 2016. City officials have touted the $110-million-plus project as aFull Story >
    City leaders say riders will now likely be able to start boarding in April of 2016. The 3.6 mile track will run from the riverfront through Over-The-Rhine. The project has a $110 million price tag.
    Full Story >
CINCINNATI, OH (FOX19) -

Duke Energy is suing the City of Cincinnati as part of a deal to determine who will cover the cost of relocating its utilities for the Streetcar Project.

The lawsuit was filed by Duke on Thursday at the Hamilton County Common Pleas Court.

As part of a 'Cooperation Agreement' reached between the City and Duke, the two parties agreed to seek a court ruling over who is responsible for the costs of relocating Duke's utilities in city streets.

On Feb. 1st, Mayor Mark Mallory announced the agreement, including an operations plan for how the utility company and the City will work in partnership once the Streetcar is up and running.

The lawsuit was filed just one day after the city announced construction bids for the Streetcar were tens of millions of dollars over what the project budget had anticipated.

The bids include the cost to construct 3.6 miles of streetcar tracks, as well as stations and a maintenance and operations facility.

A city spokesperson said the bids are being examined, and the administration is reaching out to all of the city's project partners to decide the best step forward.