Streetcar work resumes after ASG

CINCINNATI, OH (FOX19) -

Streetcar construction has started again, and that means more closures this weekend.
 
Workers was temporarily derailed while the All Star Game crowd was in town.
 
Crews will be on Main Street Friday preparing for track work between Fifth and Sixth streets.
 
The block will then close Sunday and remain closed throughout next week. It is scheduled to reopen July 24.
 
Other streetcar construction work next week:
 

MAIN STREET

Fifth to Sixth:  excavation & preparation for track installation, rail delivery  (1 week remaining)

WALNUT STREET

Fourth to Fifth: Fire hydrant modifications (1 week remaining)
Ninth to Central Parkway: Masonry work (3 weeks remaining)
 
RACE STREET


at Henry:  rail grouting and filler installation (1 week remaining)
 